Bridge Repairs

Bridge Repairs

Following extensive bridge repairs, Devonshire Road is set to fully reopen to two way traffic on Friday 24 August 2018 at around 1pm, three and a half weeks ahead of schedule.

Devonshire Road Bridge is the last bridge in a significant programme of investment which has seen a number of the town’s key bridges modernised as part of a £11.3m project to ensure they remain safe for future use. The visual benefit of which is that they’re all now cleaner, brighter bridges.

The bridge refurbishment work at Devonshire Road began on 4 June 2018. It involved repairing supporting steel beams that have corroded over the years and the walls have been clad with new red and white bricks to replace old weathered brickwork.The work has prolonged the life of the bridge for years to come.

Sign Up

Works to resurface the footway and cladding are ongoing, but meanwhile pedestrian access will be maintained. Additional road resurfacing will be carried out in the next six months. Resurfacing will be done when it’s more cost effective to do so as other works are taking place in the surrounding area.

Squires Gate Bridge

Squires Gate Bridge reopened after a four month replacement programme. The bridge reopened on 14 March 2018.

As part of the £2.2m scheme, corroded concrete and steel beams supporting the bridge were replaced to prolong the life of the bridge for years to come. It is expected that the work will give the bridge an extra 120 years of life.

Squires Gate Bridge being reopened to traffic

The bridge replacement is part of a programme to fix ten of Blackpool’s bridges during the next five years at a total cost of £11.365m. The money is made up by contributions from Blackpool Council, the Department for Transport’s Challenge Fund and the Lancashire Enterprise Partnership’s Growth Fund.

The next bridge to be improved will be Devonshire Road Bridge in the summer.

More About Squires Gate Bridge Repairs

Essential work at Squires Gate Bridge began on Tuesday 7 November 2017 as part of Blackpool’s bridges improvement programme.

Squires Gate Bridge from Google Maps
Squires Gate Bridge looking towards the sea. Pic: Google maps

Work involved replacing the carriageway and supporting steel and concrete beams. While the work was undertaken Squires Gate Bridge was closed to vehicles between Sandbridge Place and Hillcrest Road.

Over time, the reinforced concrete beams and steel supporting Squires Gate Bridge had become corroded. They had to be replaced to ensure the bridge can remain open for years to come.

State of repair of Squires Gate Bridge
State of repair of Squires Gate Bridge

Harrowside Bridge

Published 27.7.17

Harrowside bridge closed due to safety issues highlighted during an inspection. Due to serious deterioration, engineers have identified the bridge as a safety risk to the public. It closed to traffic Wednesday 26 July 2017 whilst a repair plan is put in place.

State of repair at Harrowside Bridge, Blackpool
State of repair at Harrowside Bridge

Harrowside Bridge Blackpool, photo from Google maps
Harrowside Bridge Blackpool, photo from Google maps

Pedestrians could still use the footpath during the closure and businesses on the bridge remained open as usual.

State of Repair at Harrowside Bridge

Recent checks have revealed that steel reinforcements have corroded by 40% which means that essential repair work will need to take place.

Deterioration at Harrowside Bridge Blackpool

Waterloo Road Bridge

Published 2 July 2017

Essential repair work to Waterloo Road bridge began on Monday 3 July 2017. Work took place to strengthen the existing structure, lasted around six weeks and is now complete.

Waterloo Road Bridge repairs, photo from Google maps
Waterloo Road Bridge repairs, photo from Google maps

The maintenance work involves highway realignment over the bridge deck. This means that the width of the carriageway over the bridge has been reduced, to reduce the load on the edge beams under the footway.  The taxi rank and loading bay positioned on the bridge deck were removed as a result of the highway realignment works.

The four-span bridge is said to have been constructed in the early twentieth century and originally supported the road over railway tracks which led to the old Blackpool Central Station.

Plymouth Road Bridge 

Like a number of Blackpool bridges, Plymouth Road Bridge (also known as Crossleys Bridge) was suffering from age. It’s one of the 10 bridges across the town to undergo significant investment over a period of five years. Plymouth Road Bridge reopened to drivers on Friday 7 April 2017 following a six month repair programme.

Crossleys bridge, January 2017, photo by Steve Palmer
Crossleys Bridge in January 2017, photo by Steve Palmer

This bridge is adjacent to the former B&Q / Warbreck Hill / Mowbray Drive industrial estate area.

The third phase of the bridge repair programme was completed at the end of June 17, ahead of schedule, and saw the utilities from the temporary footbridge diverted back into the highway. The final surface has now been completed which provides a much smoother surface for road users.

With the final phase of engineering works complete, the eighty-year-old bridge reopened to two way traffic with all four lanes in operation once again.

The earlier second phase of the bridge repair programme saw the eighty year old bridge replaced with a stronger and higher alternative.

The bridge has been raised in order for electrification works to the railway line underneath to take place. Both schemes have taken place at the same time to minimise disruption.

As part of the £6.1m scheme, the deck of the bridge has been replaced due to corrosion. The corrosion on the bridge was significantly high, with the chloride based corrosion of the concrete rated as being up to 6%, far above the recommended level of 0.3%.

£1m of external funding for Plymouth Road bridge has also been received from Network Rail in order to raise the height of the new bridge, enabling electrification works of the train line underneath.

Princess Street Bridge

The rusty bridge at Princess Street, which was on the verge of being closed, was demolished and rebuilt in 2015/16.

Demolition of Princess Street Bridge

Work on Princess Street bridge, which carries Seasiders Way, began at the start of November 2015. More work on removing the existing surroundings took place over the winter, and the new bridge was installed in early 2016.

As well as replacing the bridge, landscaping around the area provided stepped access from Princess Street on to Seasiders Way, as well as making the area brighter and safer for local residents.

As well as being in a decrepit state, the old bridge was also a hotspot for anti-social behaviour, with the dark corridor often complained about by local residents.

More about Blackpool Bridge Repairs

Ten bridges across Blackpool will undergo significant investment over a period of five years in order to spread out the works and reduce disruption to motorists. Ultimately the works will keep transport in Blackpool moving long into the future.

The maintenance programme to repair 10 Blackpool bridges is at a total cost of £11.365m.

The money is made up by contributions from Blackpool Council, the Department for Transport’s Challenge Fund and the Lancashire Enterprise Partnership’s Growth Fund.

Current information here

Find out More

Have a look at the Live Blackpool website homepage for more of the latest updates.

If you love the Fylde Coast you ought to sign up for our weekly email newsletter. It’s packed full of interesting things and will arrive in your inbox all 52 weeks of the year.

Join us on Facebook at our Visit Fylde Coast Facebook Group

Don’t forget to follow us on Twitter @visitFyldeCoast

What do you think? Leave a comment

Leave a reply

Your email address will not be published. Required fields are marked *